General information about the simplified procedure to get connected to electricity supply (up to 150kW)
- New clients or those who are increasing permitted capacity (without changing reliability category)
- Those business clients who need no more than 150 kW of electrical power
- Owners of the object where the electricity supply will be connected
- The object where electricity supply will be connected is located not more than 500 m from the electricity distribution grid of ESO
A customer which has been ensured security category 1 and requires an uninterrupted supply with electricity (for specifically important category 1 electricity receiver groups), is required to arrange and ensure the electricity supply from own autonomous electricity sources (batteries, electricity generators, etc.) with the properly operating automatics able to connect a disconnected Group 1 electricity receiver to the power supply sources concerned.
For customers choosing security category 1 and category 2, the connection fee is multiplied by two.
All other consumers except household consumers pay 40% of the approved connection fee.
Rates listed below are applied for connecting new permitted capacity up to 500 kW.
Connection fees from 1st April, 2019:
customer group | RATE FOR THE INSTALLATION OF OR INCREASE BY 1 KW OF PERMITTED CAPACITY (INCL. VAT) |
RATE FOR THE BUILDING OF 1 M OF ELECTRICITY NETWORK (incl. vat) |
Group I (Permissible capacity < 30 kW, no network reconstruction or project needed) |
10,10 | - |
Group II (Permissible capacity < 50 kW) |
56,02 | 15,27 |
Group III (50 <= permissilbe capacity <= 100) |
30,32 | 11,64 |
More information about customer groups can be found in the website of National comission for energy control and prices.
Please learn about the electricity tariff plans, and select the one that suits you best.
Tariff plans
In case the connection of a customer's electricity facilities to the distribution electricity networks of AB ESO requires carrying out the works not related to building the electricity network, and no separate project is required for performing the works | up to 25 calendar days1 whether the project plan is prepared both by selected designer and by ESO |
In case the connection service expenses (according to the estimate value) does not exceed EUR 25,000 excl. VAT, and the customer has selected an annual contractor for performing the connection works |
up to 45 calendar days1 when the project is prepared by selected designer up to 85 calendar days1 when the project plan is prepared by ESO |
When the connection service costs (according to the estimate value indicated in the scheme) exceeds EUR 25,000 excl. VAT, but is under EUR 44,000 excl. VAT. |
up to 60 calendar days2 when the project is prepared by selected designer up to 120 calendar days2 when the project plan is prepared by ESO |
When the connection service costs (according to the estimate value indicated in the scheme) exceeds EUR 44,000 excl. VAT. |
up to 90 calendar days2 when the project is prepared by selected designer up tp 150 calendar days2 when the project plan is prepared by ESO |
When for the purpose of carrying out the connection works the operator organises the public procurement of works, and in case securing and/or improving of the connected electricity equipment, or the parameters of the distribution and/or transmission network, require the installation and/or reconstruction of 330 kV, 110 kV, 35 kV overhead or cable power lines, 330/110/10 kV, 110/35/10(6), 110/10(6) kV, 35/10 kV transformer stations and distribution units, except for the cases when at the time of signing the contract no scheme for the connection of the customer's electric equipment to the power networks as been drawn up , and there is no possibility to indicate the exact term for the connection of the customer's power equipment. | up to 12 months2 whether the project plan is prepared both by selected designer and by ESO |
1 – from the day of payment of the connection fee
2 – from the signature of the contract on works with the contractor who has won the public procurement tender.
When providing to a customer a requested service for the transfer of ESO electricity equipment, a contractual term for the provision of the service is established; the term starts from the date of signing the contract with the contractor performing the electricity equipment transferring works.
The term for the provision of the service may be longer, when a longer term for the completion of the works is required due to their seasonal character, the peculiarity and the scope of the project, or other reasons beyond the control of ESO.
- New clients or those who are increasing permitted capacity (without changing reliability category)
- Those business clients who need no more than 150 kW of electrical power
- Owners of the object where the electricity supply will be connected
- The object where electricity supply will be connected is located not more than 500 m from the electricity distribution grid of ESO
Simplified procedure to get connected to electricity supply
If connecting to the electricity system requires project drawings, it will be specified in the connection service requirements issued by ESO.
In case the simplified procedure project plan works are performed by ESO, the project plan work price will be set according to the rate provided by the contractor that has concluded a contract with ESO or according to the rates of the services acquired by way of public procurement.
customer | eso |
For the simplified procedure, submit the application for ordering the service using the self-service website www.manogile.lt. |
|
CUSTOMER | ESO |
- At the self-service website www.manogile.lt; |
We will notify you of the course of drawing up the contracts on the connection service, and the electricity transmission service |
We will install electricity meter and start the electricity supply after:
The following steps have to be completed in order to finalize the connection to electricity system:
customer | eso |
|
We will connect the customer to ESO network within 5 working days from the completion of the electricity network construction works and receipt of the Contractor Certificate. |